The new Bay Bridge East Span’s marquee self-anchored suspension span (SAS) is getting tauter and taller this week. Early in the morning on Tuesday, August 14, crews began the laborious and delicate process of tightening the vertical suspender cables as the first step in transferring the SAS’ weight from temporary supports underneath the bridge decks to the cable suspension system above the decks. And on Wednesday, a crane perched 500-plus feet in the air started to crown the span’s signature tower with four pieces known as tower heads, which will bring the tower to its full 525-foot height.  

At a press briefing this morning at Aquarium of the Bay Theater in San Francisco, the spotlight was on the load transfer operation, which Bay Bridge spokesman Bart Ney called the biggest “lift” on a project that has seen many lifts of massive steel deck and tower pieces. The initial phase under way this week involves the tightening of eight pairs of suspender cables, which together are supporting 10 percent of the bridge’s load. “It’s an amazing, historic day for the Bay Bridge,” Ney said.

Over the next three months, hydraulic jacks at the edge of the twin bridge decks will sequentially tighten all 200 vertical cable strands. Also in play now is the centerpiece of the suspension system: the nearly mile-long main cable that loops around the decks and tower, and from which the suspender cables hang. Whereas bridge cable systems are typically anchored into the ground, the SAS main cable is anchored into the deck itself, hence the term self-anchored suspension span.

As the suspension system is tightened and adjusted, it gradually will lift the 35,200-metric ton steel structure off the underlying temporary trusses. In the process, the main cable will push out to the sides, the tower will be released from its tilt toward Yerba Buena Island and stand upright, and the SAS’s twin decks will compress and shrink a bit.



“Things are moving and the forces are huge,” said Brian Maroney, Caltrans’ chief engineer for the East Span project, who also was on hand at the press briefing. “This is a series of complex engineering processes that we’re going to have to watch closely.”

— Brenda Kahn

SAS Load Transfer Preview

Submit your comment

In order to receive a reply to your comment, please provide an email address.

Plain text

  • No HTML tags allowed.
  • Web page addresses and email addresses turn into links automatically.
  • Lines and paragraphs break automatically.